Reception and landscaping
St. Aidan's Anglican Girls' School

Project Size
500m2
Project Cost
$500k - $1M
Project Duration
8 weeks

We delivered a fast-tracked, eight-week transformation of key campus areas. The project involved converting a 25m pool into a landscaped space and upgrading the school’s reception. Our team coordinated with trusted partners to deliver high-quality landscaping and custom joinery. The result is a functional and aesthetically enhanced environment that seamlessly integrates with the school’s identity, demonstrating our expertise in delivering high-impact projects under challenging conditions.

  • Reception fitout
  • Live campus environment
  • Landscaping
Capabilities
FitoutRefurbishment
Engagement Type
D&C
Sector
  • Education
Subsector
  • Independent Schools
  • Student Facilites
Specialty
Live EnvironmentOccupied SpaceValue Engineering
Team
Fay AmiriSebastian Bornkessel

The Brief

St Aidan’s Anglican Girls’ School engaged us to transform key areas of their campus over the summer holidays, delivering a major transformation within just eight weeks. The scope included converting the existing 25m pool into a landscaped space and upgrading the school’s reception to enhance functionality and first impressions. The challenge lay in executing the works within a tight timeframe while overcoming complex site access and unpredictable weather conditions. Precision logistics were required to transport and install 10 large established trees at the heart of the school.

Our contribution

To ensure smooth project execution, our team implemented detailed planning and strategic coordination from the outset. Led by Fay Amiri and Sebastian Bornkessel, we worked closely with trusted partners to bring the vision to life. Brooke’s Blooms, Concrete Applications and EDC Systems played a crucial role in delivering the stunning landscaping, while River City Cabinets provided custom joinery that elevated the reception space. Our commitment to efficiency and collaboration ensured the project was delivered seamlessly within the school’s operational environment.

 

 

The remarkable project outcome

The result is a revitalised outdoor space and an upgraded reception area that seamlessly integrates with St Aidan’s identity and vision. By overcoming logistical challenges and adhering to the strict timeline, we created an environment that enhances both function and aesthetics for students, staff, and visitors alike. This transformation stands as a testament to our expertise in executing high-quality, time-sensitive projects that make a lasting impact.

Short timeframe, big impact – delivering remarkable results for the St Aidan’s community.