This purpose-built, standalone commercial kitchen supports TSMC's growing network of stores. Under a D&C contract, we resolved a major program risk early, avoiding delays caused by a rooftop plant deck. Throughout delivery, we collaborated closely with consultants and certifiers to ensure the space met all food-grade requirements and achieved full certification. The result is a high-performance production facility delivered on time, ready to scale with TSMC’s continued growth.

  • Commercial kitchen
  • Plant deck
  • Structural steel
Capabilities
Fitout
Engagement Type
D&C
Sector
  • Hospitality
Subsector
  • Commercial Kitchen
Specialty
Live EnvironmentOccupied Space
Team
Troy RootsWarrin Orman

The Brief

With their original kitchen operating at full tilt, The Standard Market Company (TSMC) needed to scale up to keep pace with demand across their expanding network of stores. Their solution: a purpose-built, standalone commercial kitchen designed to centralise production and streamline delivery to multiple retail locations. The program was tight, and the operational need was immediate – every design and construction decision had to support a fast, compliant handover.

Our contribution

We were engaged under a Design and Construct (D&C) contract to deliver the complete fitout of the new production kitchen. Early in the design phase, the plan included a rooftop plant deck. However, this proved time-prohibitive and risked pushing out the program. To avoid delays, we engineered an internal solution – reinforcing the structure of the roof from within to support the mechanical plant. This approach preserved both program and functionality.

Throughout the project, we worked closely with consultants and certifiers to ensure full compliance with food-grade standards. Our collaborative approach allowed us to navigate certification requirements, respond to evolving design needs, and maintain momentum without compromising quality.

The remarkable project outcome

We delivered a high-performance commercial kitchen, fully certified and operational on time. By thinking practically and acting decisively, we avoided program delays and created a space that can scale with TSMC’s continued growth. The new facility has become the backbone of their production operations – and a great example of what’s possible when flexibility, expertise, and smart decision-making come together.